Is it possible to retain the plan before starting a project and compare it to the actual plan?

Modified on Fri, 26 Jan at 3:38 PM

Yes, it is possible.

In ACTY'S, you can retain the plan that was finalized before starting the project as “Baseline”.

  • By executing “Set to Baseline” command for the entire file or selected Bars only, you can register the Baseline in Property of each Bar.
  • By setting to display “Baseline Bar” with “Bar Layout” function, the Baseline schedule can be displayed.



By comparing "Baseline Bar" with "Active Bar", you can visually check the gap between the Baseline and the actual schedule.



[Display settings for Baseline Bar and Active Bar with Bar Layout function]



[You can check the gap between plans and actuals]






C_KTZ_FEA_5_2205_00008_00

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article