Yes, it is possible.
In ACTY'S, “Constraint” can be used to represent the execution order for Tasks and their dependencies.
Example:
When activity A is finished, activity B can be started
When activity A is started, activity B can also be started
It is expressed as an arrow connecting Bars in BarChart Area of ACTY'S.
Types of Constraint
There are four types of Constraints as follows:
- FS (Finish-to-Start)
- FF (Finish-to-Finish)
- SF (Start-to-Finish)
- SS (Start-to-Start)
C_KTZ_FEA_5_2205_00006_00