Is it possible to set important schedules (construction start date, delivery date, etc.) that cannot be moved?

Modified on Thu, 25 May, 2023 at 3:05 PM

Yes, it is possible.

  • For important schedule which cannot be changed, you can create a Bar in the Milestone Area at the top of the bar chart to fix and display it as “Milestone”.
  • If you want to fix a specific activity, set “Be Fixed” in “Time Analysis Settings” of Bar Property.



Fixed date is displayed with "¤" mark which can be used as an indicator for process management.



[Fixed display of important schedule]




What is Milestone? 
It is a management point for a Project which set to the particularly important date such as delivery or deadline.
By dragging the mouse in Milestone Area, you can create a Milestone Bar.



[Fix a Bar by setting it to not move]






C_KTZ_PMG_4_2205_00048_00

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article