Yes, it is possible.
- In addition to the actual schedule information, each activities in ACTY'S can also hold the baseline schedule information.
- The baseline can be displayed as “Baseline Bar” on the bar chart and compared to the latest actual.
- By using “Bar Layout” function and setting it to display both the “Baseline Bar” which represents the Baseline schedule and the “Active Bar” which represents the actual schedule, plans and actuals can be displayed at the same time for check and comparison.
[Display settings for Baseline Bar and Active Bar with Bar Layout function]
[Plans and actuals can be shown and checked together]
The Baseline Bar for the selected activity is highlighted in a different color to make it easier to compare with the actual.
What is Bar Layout?
This is a function that allows you to specify the type of Bar to be displayed in the bar chart or the property items to be displayed along with the Bar for each View.
You can freely customize the display items so that you can check the necessary information on the bar chart screen without opening the property window of the Bar.
C_KTZ_PMG_4_2205_00047_00
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article