Is it possible to check the difference between planned and actual on a bar chart?

Modified on Thu, 25 May, 2023 at 10:26 AM

Yes, it is possible.

  • Both baseline schedule and actual schedule are retained in an activity.


[Bar Property window]




  • By using “Bar Layout” function to display both the baseline schedule and the actual schedule, you can compare and check the planned and actual of activities.


[Example of Baseline Bar (upper) and Active Bar (lower) display]



What is Bar Layout? 
This is a function that allows you to specify the type of Bar to be displayed in the bar chart or the property items to be displayed along with the Bar for each View. 
You can freely customize the display items so that you can check the necessary information on the bar chart screen without opening the property window of the Bar.






C_KTZ_PMG_4_2205_00046_00

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article